How Long a Pool Remodel Takes in Brevard County, Week by Week

· 4 min read

A straight resurface is about a week or two from drain to refill. A full remodel, with tile, coping and deck, is more like four to six weeks on site.

Neither number includes permitting, and permitting is where most of the waiting happens. Below is what each week looks like and what moves the dates.

Why is the work time shorter than the project time?

Because a pool remodel is a series of short jobs with drying time between them.

Chipping out an old finish takes a day or two, and applying a new one takes a day. Tile work, plumbing, an inspection and a cure fall between them.

Nobody is at your house for most of the calendar.

That gap surprises people, so a good contractor tells you the crew days and the calendar days as two different numbers.

What happens week by week?

This is a full remodel. A resurface skips weeks two and three.

Before week one. Survey, design, quote and permit. The permit is submitted once you sign, and the clock on it belongs to the county.

Week one. Drain the pool, chip out the old finish, and take off the old tile and coping. This is the loud, dusty part, and it is over quickly.

Week two. Plumbing changes, new returns, main drain covers to current code, and any structural repair the drained shell has shown up.

Week three. Tile and coping go on. Deck work happens alongside, where the deck is part of the job.

Week four. The interior finish goes on. Then the pool gets filled the same day, because a new finish should not dry out.

The week after filling. Daily water chemistry, brushing, and the start up schedule the finish maker sets. This part is not optional and it decides how long the finish lasts.

What pushes the dates?

Five things, in rough order of how often they bite.

  1. Permitting. It belongs to the county and no contractor controls it.
  2. Rain. Gunite, plaster and deck work all need dry weather.
  3. Inspections. They are scheduled, not instant, and the job waits for them.
  4. Tile lead times. A tile chosen from a catalogue can add weeks on its own.
  5. What the drained pool shows. A shell nobody has seen empty for fifteen years sometimes has news.

Number five is the one worth planning for. Ask what happens to the schedule if something is found, before it is found.

Does the time of year change anything?

Yes, in two ways here.

Our wet season is the summer, and rain delays outdoor concrete work. A remodel booked for June has more weather risk than the same job in February.

The other pressure is demand. Everybody wants the pool ready for spring, so winter fills up fast in Brevard. Booking in autumn for a spring finish is easier than booking in March.

How long can the pool be empty?

Less time than people expect. This is a safety point, not a scheduling one.

We build on sand with a high water table. Groundwater outside an empty shell pushes up on it, and a shell can lift. So the drain is planned, the hydrostatic relief valve gets checked, and the pool does not stand empty waiting for a delivery.

A contractor who drains your pool and then orders the tile has the order wrong.

What to do next

Ask for two dates and one condition: the crew days, the calendar days, and what happens to both if the empty shell shows a problem.

Our pool remodeling page covers what a remodel includes and how we sequence it. We have remodeled pools in Brevard and Indian River County since 1992, through plenty of wet summers. We will give you a schedule with the waiting written into it.